Bloomberg
Phase 6
919 Third Avenue MEP Riser
Overview
Layered riser coordination in one building view
Use the toggles to isolate electrical, mechanical, plumbing, and IT/AV/Security risers. Drag across the tower to rotate; scroll or pinch to zoom.
Sequence Timeline
JRM released
Jun 26
Trade awards
Jul 1-Aug 7
Start
Aug 3
GC PO
Aug 14
Substantial
Jan 28
Complete
Feb 11
Shaft accessAug 17-Sep 11, 2026 / 4 wks
HVAC riserOct 12, 2026-Jan 13, 2027 / 13 wks
Plumbing roughOct 19-Oct 23, 2026 / 1 wk
Bus ductOct 12, 2026-Jan 25, 2027 / 14.6 wks
Telecom riserOct 12, 2026-Jan 28, 2027 / 15.2 wks