Phase 6

919 Third Avenue MEP Riser

Overview

Layered riser coordination in one building view

Use the toggles to isolate electrical, mechanical, plumbing, and IT/AV/Security risers. Drag across the tower to rotate; scroll or pinch to zoom.

Sequence Timeline

00.0s
JRM released Jun 26 Trade awards Jul 1-Aug 7 Start Aug 3 GC PO Aug 14 Substantial Jan 28 Complete Feb 11
Shaft accessAug 17-Sep 11, 2026 / 4 wks
HVAC riserOct 12, 2026-Jan 13, 2027 / 13 wks
Plumbing roughOct 19-Oct 23, 2026 / 1 wk
Bus ductOct 12, 2026-Jan 25, 2027 / 14.6 wks
Telecom riserOct 12, 2026-Jan 28, 2027 / 15.2 wks

Phase 6

2D Logistics Plan Composites

Layers

Adjust

Floor 29 electrical plan layer Floor 29 logistics overlay layer Floor 35 HVAC plan layer Floor 35 electrical plan layer Floor 35 telecom plan layer Floor 35 fire alarm plan layer Floor 35 fire protection plan layer Floor 35 structural framing plan layer Floor 35 logistics overlay layer Floor 41 HVAC plan layer Floor 41 electrical plan layer Floor 41 telecom plan layer Floor 41 fire alarm plan layer Floor 41 fire protection plan layer Floor 41 structural framing plan layer Floor 41 logistics overlay layer Floor 42 HVAC plan layer Floor 42 electrical plan layer Floor 42 telecom plan layer Floor 42 logistics overlay layer Floor 43 HVAC plan layer Floor 43 electrical plan layer Floor 43 telecom plan layer Floor 43 logistics overlay layer Floor 44 HVAC plan layer Floor 44 electrical plan layer Floor 44 telecom plan layer Floor 44 fire alarm plan layer Floor 44 fire protection plan layer Floor 44 structural framing plan layer Floor 44 logistics overlay layer

Phase 6

Key Shaft Elevation

44 43 42 41 40 39 38 37 36 35 34 33 32 31 30 29 22
5E22-45
5D34-40
8E37-44
7D33-36
9E33-36

Electrical

Electrical riser diagram for 919 Third Avenue

Mechanical

Mechanical riser diagram for 919 Third Avenue

Plumbing

Plumbing riser diagram for 919 Third Avenue

IT / AV / Security

IT AV Security riser diagram for 919 Third Avenue